Breakwater Roboh di Pulau Karya Diperbaiki
.
photo Suparni - Beritajakarta.id

Breakwater Repair Work on East Side of Karya Island Has Reached 80 Percent

Our target is in two days ahead. Hopefully it can protect the Karya Island from abrasion and high waves

The Thousand Islands Water Resources (SDA) Sub-agency is seen repairing the damaged breakwater on the east side of Karya Island, Panggang Island Urban Village, North Thousand Islands Sub-district. Currently the progress has reached 80 percent.

Thousand Islands SDA Sub-agency Head, Hendri said the repairs carried out by the officers included rearranging the massive cube that collapsed due to the brunt of the high waves some time ago. Then the massive cube was tied with alternating wire to make it strong and sturdy.

Untung Jawa Island Breakwaters are Being under Maintenance

"The repair that takes 210 meters long has been conducted since early June," he expressed, Friday (6/4).

To conduct it, his side had deployed as many as 10 personnel to the location.

"Our target is in two days ahead. Hopefully it can protect the Karya Island from abrasion and high waves," he stated.

Linked News
Popular News indeks
  1. Duren Sawit PTSP Holds Door-to-Door Servies at Pondok Kelapa TPU until Thursday

    access_time15-05-2024 remove_red_eye739 personNurito
  2. Aiming to Global City, Jakarta Prioritizes the Development of Environmentally Friendly Waste Processing

    access_time13-05-2024 remove_red_eye627 personFolmer
  3. Commission D: RDF Construction in Rorotan Has Many Benefits

    access_time13-05-2024 remove_red_eye626 personFolmer
  4. 35 Toddlers in Kedoya Selatan Received Assistance with Nutritious Additional Food

    access_time13-05-2024 remove_red_eye579 personTP Moan Simanjuntak
  5. 42,878 Tourists Swarm Monas Area

    access_time12-05-2024 remove_red_eye411 personBudhi Firmansyah Surapati